OK, I'm probably missing what is the problem here, but you can:
    - define your variable for determining when the loop ends, and this variable will be updated by serverside activity.
    - write proper transition condition using this variable, and introduce transition OTHERWISE, if condition is not satisfied (engine should follow this OTHERWISE transition when the loop has to be exited)
    - define some ForamalParameters for the process that will be referenced from a subflow activity of your main process
    - when defining Subflow activity, go to Subflow tab, and add actual parameters that will correspond to subflow formal parameters (you can find some examples of passing parameters to subflow in XPDL processes comming with JaWE, i.e. Business_Example.xpdl). This actual parameters can be either "main" process variables, or some expressions if corresponding subflow's formal parameter is IN type parameter.
 
Sasa.
 
----- Original Message -----
Sent: Tuesday, April 06, 2004 2:54 PM
Subject: RE: [jawe] Looping in Jawe

1. No, Loop should be outside of the subflow process.
2. The variable determining the condition will be set in a previous activity by some serverside activity.
3. I am using OBE engine now
4. It also need to pass variables to this subflow (formal parameters)
 
In another instance Loop can be inside the subflow as long as the variable determining the condition is passed in.
 
Thanks
Venu
-----Original Message-----
From: Sasa Bojanic [mailto:sasaboy@xxxxxxxxxxxxx]
Sent: Tuesday, April 06, 2004 8:52 AM
To: jawe@xxxxxxxxxxxxx
Subject: Re: [jawe] Looping in Jawe

Maybe my question wasn't clear enough - do you need to have loop inside subflow process, or should subflow activity be the part of the loop? Also, I suppose you wan't to have conditional loop that will execute loop activities until condition for exiting loop is met? If so, do you want variable determining the condition to be updated manually by user, or automatically by some serverside activity? Which engine are you using?
 
Regards,
Sasa.
 
----- Original Message -----
Sent: Tuesday, April 06, 2004 2:37 PM
Subject: RE: [jawe] Looping in Jawe

Yes, in a nutshell that is what I would like to do. Basically I would like to implement a for loop, where the loop index is available in the parent process.
With in the loop it should spawn the subflow, passing in some parameters. The subflow has a manual activity.
 
Thanks
Venu
-----Original Message-----
From: Sasa Bojanic [mailto:sasaboy@xxxxxxxxxxxxx]
Sent: Tuesday, April 06, 2004 6:13 AM
To: jawe@xxxxxxxxxxxxx
Subject: Re: [jawe] Looping in Jawe

Hi,
 
can you explain a little bit closer what do you need - I can't comprehand it?
Do you need to create a loop with some special loop condition passed through formal parameters of the subflow?
 
Regards,
Sasa.
----- Original Message -----
Sent: Tuesday, April 06, 2004 12:30 AM
Subject: [jawe] Looping in Jawe

Does any body know how to create a looping sub-process in Jawe:

A parent process should create a child process defined as subFlow based on the looping parameter defined in the parent process. It should also pass an argument to the child process based on the looping parameter.

Any help is appreciated.